Cancelled: McLennan building complete electrical shutdown scheduled – April 6, 2019, from 6:00am to 10.00pm
Scheduled Maintenance Report for ITS System Status
Completed
McLennan building complete electrical shutdown has been cancelled and will be rescheduled at a future date.
Posted Mar 20, 2019 - 10:12 EDT
Update
We will be undergoing scheduled maintenance during this time.
Posted Mar 12, 2019 - 08:22 EDT
Scheduled
The ITS Data Centre (DCB) will be operating on emergency power Saturday April 6th, 2019 from 6:00am to 10:00pm during a scheduled F&S building electrical maintenance event which requires a complete shutdown of the building electrical supply for 16 hours. Emergency power will be supplied to the data centre by a permanently-installed diesel generator and 48 hours (at current IT and HVAC loads) of on-site diesel fuel supply, which will be replenished daily should the need arise.

During the maintenance window, there will be no base-building power or cooling supply available. While extremely unlikely, a failure of either the generator or the primary cooling plant during the maintenance period could, in the worst case, force a complete shutdown of the data centre facility. DCB has been designed, built and maintained to operate otherwise normally and indefinitely under these conditions, without impact to any services.
Posted Mar 12, 2019 - 07:37 EDT